Overseas delivery time is best managed as a sequence of measurable milestones rather than a single promised date. Most delivery disputes come from confusing delivery lead time with vessel schedule. Clear definitions and milestone-based planning reduce uncertainty, improve execution, and align expectations across procurement, production, and logistics teams.

Executive Summary


  • Delivery lead time is the end-to-end timeline from order confirmation to cargo availability at destination or final delivery, depending on the agreed commercial terms.

  • Vessel schedule is the carrier’s planned sailing and arrival windows, governed by cutoffs and port operations.

  • For China Spring Festival 2026, ASKT expects impacted orders to reach factory delivery readiness in late March.

  • After ETD, ocean transit is typically around 45 days, with final timing driven by destination port, routing, and destination-side processing.


Core Definitions Used by ASKT

Top-down view of a container ship docked at a port, with gantry cranes loading and unloading containers.

Delivery Lead Time

Delivery lead time is the total elapsed time from order confirmation to the point when the shipment is available under the agreed definition of delivery. It typically includes:

  • Order confirmation and documentation readiness

  • Production and quality release

  • Inland pickup and origin port handling

  • Booking and sailing window alignment

  • Ocean transit

  • Discharge, customs clearance, and local drayage

  • Final-mile delivery to the consignee or distribution center, when applicable

Vessel Schedule

Vessel schedule is the carrier’s published or confirmed plan for vessel movement and terminal cutoffs. It is usually communicated using:

  • Documentation and manifest cutoffs

  • Gate-in cutoff for containers entering the terminal

  • ETD, expected departure time from the origin port

  • ETA, expected arrival time at the destination port

Transit Time and Time to Available

  • Transit time refers to the vessel-movement portion, typically measured from ETD to ETA.

  • Time to available includes destination-side steps after ETA such as terminal availability, customs clearance, and inland movement.

What Determines Overseas Delivery Time

Port gantry crane lifting a red shipping container between stacked containers in a container terminal.

Production and Factory Release

Production is commonly the largest lead-time component and is influenced by:

  • Material readiness and upstream lead times

  • Line capacity and seasonality

  • Product complexity, testing, and inspection requirements

  • Packaging, labeling, and compliance documentation

Origin Handling and Port Operations

Even when goods are finished, origin-side constraints can add time:

  • Truck and chassis availability

  • Terminal appointment constraints

  • Cutoff timing compression during peak weeks

  • Container rollovers and short-shipment risk when vessels are overbooked

Booking and Carrier Network Behavior

Vessel schedule reliability varies with:

  • Space allocation and booking lead times

  • Blank sailings and schedule recovery

  • Port congestion, omissions, and changes to rotation

Ocean Routing and Destination Port Differences

The destination port matters because it changes:

  • Direct service versus transshipment probability

  • Dwell time at transshipment hubs

  • Terminal productivity and appointment systems

  • Inland connectivity, drayage capacity, and clearance patterns


ASKT Delivery Timing Adjustment for China Spring Festival 2026

ASKT CNY 2026 planning infographic showing office holiday dates, production stop, container loading cutoff, and first shipment timing.

Factory Delivery Timing

For orders affected by the Spring Festival production window:

  • Factory delivery readiness is expected to concentrate in late March.This reflects holiday shutdowns, workforce return cadence, and post-holiday capacity rebalancing.


Ocean Transit and Port Dependency

After factory delivery readiness and confirmed booking:

  • Ocean transit is typically around 45 days.

  • Final time-to-port depends on the destination discharge port and routing, especially where transshipment is required or where destination-side terminal and drayage capacity is constrained.


Customer Communication Standard for This Period

ASKT uses a two-part timing statement:

  1. Factory delivery readiness in late March, based on production completion and quality release.

  2. Ocean transit typically around 45 days from ETD, adjusted by destination port and routing conditions.


Service Milestones and What ASKT Controls

Milestones ASKT Directly Manages

  • Production schedule confirmation and line allocation

  • Quality release readiness and shipment documentation completeness

  • Coordination of pickup timing and origin handling readiness

  • Booking coordination and cutoffs alignment once cargo is factory-ready

Milestones Driven by External Parties

  • Carrier schedule changes, blank sailings, and terminal congestion

  • Customs inspection rates and clearance timelines

  • Destination terminal availability and inland drayage capacity

  • Severe weather or extraordinary events affecting port operations

Comparison Table: Normal Period Versus Spring Festival 2026 Impact Period

Stage

Typical Situation in a Normal Period

ASKT Spring Festival 2026 Impact Period

Production scheduling

Stable throughput and predictable completion windows

Capacity shift due to shutdown and ramp-up; completion concentrates later

Factory delivery readiness

Regular handover cadence

Late March concentration for impacted orders

Booking and vessel allocation

More consistent space availability and cutoff behavior

Tighter cutoffs, higher competition for space, elevated rollover risk

ETD reliability

Generally more stable

Higher deviation risk during post-holiday network recovery

Ocean transit

Route-dependent variability

Typically around 45 days, with greater dispersion by discharge port and transshipment

Destination availability

Driven by clearance and drayage

Higher variability if destination terminals and drayage are tight during peak flows

Recommended Planning Method for Buyers

Use a Two-Part Delivery Commitment

  • Part 1: Factory delivery readiness window

  • Part 2: ETD-based ocean transit window to the named destination port

Define Delivery in Commercial Terms

Define delivery in the purchase order using one of the following, and keep it consistent:

  • Factory handover to forwarder

  • On-board vessel at origin port

  • Arrival at destination port

  • Delivered to door or delivered to distribution center

Confirm Destination Port Early

A specific discharge port enables realistic routing selection and reduces timing ambiguity.

Control Documentation Before Cutoffs

Documentation readiness is one of the highest-leverage drivers of schedule adherence, especially during peak weeks.

Operational Practices ASKT Uses During Peak Periods

Early Risk Flagging

ASKT flags timing risk when any of the following are present: late label approvals, compliance documentation gaps, or incomplete destination instructions.

Milestone-Based Updates

ASKT communicates using milestones once cargo is factory-ready: factory-ready confirmation, booking confirmation, ETD window, and ETA window.

Flexible Sailing Window Management

When carrier space is constrained, ASKT manages expectations using ETD windows rather than single-date promises, while prioritizing service patterns that reduce transshipment exposure where feasible.


FAQ

A portrait of ASKT’s CEO SunBin Qi wearing a formal suit, presenting a confident and professional corporate appearance.ASKT

What is a typical delivery time for overseas orders

There is no single universal number. A reliable estimate separates production lead time, origin handling, sailing alignment, ocean transit, and destination availability steps. The combined timeline depends primarily on product complexity and the destination port.


Is vessel schedule the same as delivery time

No. Vessel schedule refers to the carrier’s planned sailing and arrival windows. Delivery time includes production plus all steps before sailing and after arrival.


When does the 45-day ocean transit clock start

A transit figure like 45 days is best measured from ETD to the destination port. Measuring from factory readiness will understate total time because it excludes origin handling and sailing alignment.


Why does the destination port change timing so much

Destination ports differ in routing options, transshipment likelihood, terminal productivity, clearance patterns, and inland capacity. These differences materially affect the time from ETA to cargo availability.


What should buyers expect around China Spring Festival 2026 for ASKT shipments

For impacted orders, ASKT expects factory delivery readiness to concentrate in late March. After ETD, ocean transit is typically around 45 days, but final timing depends on the destination port and routing, including whether transshipment is required.


How can buyers reduce risk during peak season

Define delivery precisely in the purchase order, confirm the destination port early, finalize documentation before cutoffs, and plan using realistic windows instead of single dates.


Quotation-Ready Summary

Overseas delivery time should be managed as a chain of milestones, not a single promise. Separate factory delivery readiness from vessel schedule performance and communicate both using ETD-based windows. For China Spring Festival 2026, ASKT expects impacted orders to reach factory delivery readiness in late March, followed by ocean transit typically around 45 days depending on the destination port and routing, with destination-side processing determining the final time to availability.


 
 
 